|
Home
About us
Where we are
Our climate
Our land
Our plans
Our friends
Development
Contact us
Resources
Site Map
|
Development - Let's start at the very beginning...
The first six months (January - June 2004)
|
For
the first couple of months, the main work effort was to have fences installed
on the road, western and eastern boundaries, and a culvert built across
the stock race running along the road at the front of the property. This
was the easy bit, as it was done by contractors... The next issue was
what to do with the grass that had grown to knee height. That was easy
- cut it for silage. Of course there's an easy and a hard way of doing
things......
Actually, this is where contractors come in real handy, with big toys
to do all the hard work. So a silage machine came in and cut and baled
it and off it went to the neighbour's haybarn for winter feed.
|
| |
|
Somewhere
along the way, damage was done to the side of
the stock race. Our first jobs outside the main
development plan were to rebuild the bank that
was allowing water to flood in, and to backfill
the pool that was growing by the side of the
stockrace. The race was also silted up, with
approximately 70 metres length, by two metres
breadth, and a foot of silt... that's a lot
of material to dig out by hand. I guess when
the novelty wears off we'll get machinery in
to do it. But for the moment, Project
Stockrace is keeping us gainfully occupied.
The development plan has us currently marking out the boundaries of the
blocks ready for spraying and ripping shelter belt lines, and also ploughing
over the land ready for sowing fescue in winter. No such simple solution
as GPS, the ones we can justify buying aren't accurate enough... so its
the wheel and the Mk I Eyeball to get the lines straight.
|
| |
|
The
cultivation started on 4 February, with the first ploughing of the north
western half of the land, which will be used primarily for hazelnuts,
but also for two walnut blocks and the house block. By the weekend a second
ploughing had taken place. Cultivation was
interspersed with marking out block boundary points, the well, and ripping
lines.
Of course, the original markers managed to get moved during the ploughing,
so more marking had to be done. Our consultant Stephen used his measuring
wheel during the first marking session. The odd bumpy bit made that a
tad inaccurate. We tried using our new GPS unit but with a 5m accuracy
it just wasn't up to it! Oh well, we've accepted the imitations of modern
technology and gone back to the good old 30m tape measure....
|
| |
|
 Well,
well, well. That's an expensive accessory for cleaning your boots on.
Ok, actually it's our well, which went down in the week of 23 February
2004, to a depth of around 30m (and was deepened in April to 50m, and
was removed and redrilled in July after a stone dented the pipe to the
extent the pump couldn't be installed...). In the background you can just
see the power pylon from which we will have to carry electricity 300m...
|
| |
|

This trench runs through the middle of the front blocks and down to the
front fenceline, for power cables to be run back to the nearest pylon.
After very many delays, cable finally went in some time around 10 April
(after a start of March expectation).
|
| |
|

By May, the grass seed had just started sprouting (although you could
only see the faint green haze from directly above). Malcolm had also made
an important additional investment with the purchase of a second-hand
ute.
|
|
|
|