Stage 2: Framing
 
 

 

23 May - boy they move quickly! We came up so Malcolm could see the slab before he went away, and they have half the framing up for the bottom floor already!

1 June - downstairs framing pretty much complete, beams going in between the storeys.

A bit of snow over the weekend, but only a small crust left by Monday.

7 June - Downstairs framing complete, upstairs subfloor in place.

13 June - upstairs framing well underway.

20 June - Upstairs framing complete and roof trusses starting

 

 